Construction Update


As many of you have noticed, the Wolk Center for Excellence in Nursing is starting to come out of the ground.  Concrete foundation work is nearly complete and in the next few weeks structural steel will be starting.  Site utility work will be continuing and the sidewalk into building 8 will be installed on Wednesday.  Unfortunately both sidewalks running in front of building 7 will be closed down next week for more site utility work.  From parking lot "K", please use the entry into building 8 to access the rest of the campus.  As always, we appreciate your continued support and cooperation.  If you have any question, please contact Kevin Walton at ext. 2817.

Kevin Walton
Facilities
10/03/2007