Pardon our Dust - Ongoing Parking Disruptions
Our lighting and infrastructure project is progressing ata very good pace. As a result work will be finishing up in lot H and J this week (5/22-5/26), and beginning in lot K, the small lot attached to K, and the visitor's lot. If progress continues as planned next week (5/30-6/2) will see work move into Lots A and C as well as some of our indoor work beginning in building 10.
As always, our apologies for any disruptions this may cause and please contact facilities with any questions or concerns.
Travis Sleight
Facilities
05/22/2017