Parking Disruptions - Update
Thank you everyone for your continued patience as our outdoor lighting and infrastructure project continues.
Work will be continuing along the west side of the campus through the week of 6/19-6/23. This will include work along Campus Drive as well as work in parking lots A, C, and D.
The following week (6/26-6/30) should see preparatory work beginning in lot Q.
Beginning 7/5 and continuing through 7/14 we are planning to close lot Q entirely so please plan appropriately.
Travis Sleight
Facilities
06/16/2017